Watch Our Building Process

Pick your area and floorplan
1. Pick your area and floorplan
Overview process and verify options
2. Overview process and verify options
Klausmeyer pulls permit
3. Klausmeyer pulls permit
klausmeyer-excavate
4. Excavate (digging the hole)
20181023_134211
5. Foundation and footing concrete
20181023_140103
6. Waterproofing
07-backfill
7. Backfill the foundation
Flatwork concrete for the garage, basement floor, and driveway
8. Flatwork concrete for the garage, basement floor, and driveway
Framing
9. Framing
Rough-ins (plumbing, electrical, heating/air)
10. Rough-ins (plumbing, electrical, heating/air)
Siding, roof, and brick
11. Siding, roof, and brick
Insulation
12. Insulation
Sheetrock
13. Sheetrock
Trim
14. Trim
Paint
15. Paint
16 hard surfaces2
16. Hard-surfaces (countertops, flooring)
20181023_141642
17. Finals (fixtures, final plumbing, electrical, heating/air, appliances)
Sidewalks and patios
18. Sidewalks and patios
19 deep cleaning
19. Initial deep cleaning
20 touchup paint
20. Touch-up paint
21 touch up cleaning
21. Touch-up cleaning
22 walk through
22. Walk-through
23 touch up cleaning
23. Touch-up cleaning
24 closing
24. Closing
25 move-in
25. Move-in